Crystal Creek Lift Station

Customer Parker Excavating
Owner:    Woodmoor Water and Sanitation District #1
Project:      Electric for installation of new lift station
Location:    Monument, CO

Ross Electric provided the complete electrical power system and connections for this new lift station facility. this lift station included a new electric service, underground secondary feeders, two 25HP pumps with their motor controls, lighting, HVAC, lightning protection and ground grid.

Project successfully completed Feb 2000 (C6115)